Wastewater Treatment Project Design Review & Expert Witness & Operations Consulting

Wastewater Treatment Project Design Review & Expert Witness & Operations Consulting

CP worked with the Bradford Sanitary Authority (BSA) in support of the PennVEST funding by completing a Second Opinion Project Review (SOPR) package on the preliminary design prepared by Gannett Fleming, Inc. This report included questions and suggestions, which lead to the ultimate final design. Additionally, CP was again hired to provide operations support and expert witness consulting on the issues associated with the Contract Closeout of the Construction Project.

CP was also hired to continue the work of Operations Consulting and Expert Witness Testimony.  The details are confidential.

CP also provided an improvement study for the SBR Decant Control System.